Memorial Hospital of Union County

Memorial Hospital of Union County – Administration Office Alteration

This project was completed on a seventy-five day schedule and included working under a heliport that was in use throughout. What made this interesting was the new windows that were cut into the walls had to have expertly installed shoring to support the structural integrity of the building while the helicopters were in use.

The project size was 11,000 square feet on the second floor of the Hospital. It included complete renovation of the administrative office space.  Demolition took everything down to a clean slate and then the construction brought it back to fully usable space.  It included the reception area, the work room, the Board room, the employee lounge, and all adjoining spaces.

Jeff York, Vice President of Construction, was the Project Manager for this project.        Terry Davidson also served on this project as superintendent.